Deployment of new Wi-Fi technology in All Building Areas (Projects UIT16926 - UIT16934)
Overall Project Status: Complete
Project Goals & Objectives
- Meet or exceed our SLA of minimum 5Mbps in all academic and research areas
- Cover room at capacity in all academic, research, and administrative areas
- Replacement of all existing building Wi-Fi Access Points to Aruba 802.11ac Wave 2 (Gigabit Wi-Fi)
- Replacement of all existing switches supporting Wi-Fi to Aruba/HPE gigabit switches
- Upgrade core and distribution networks supporting Wi-Fi as needed
Scope of Work
- Buildings: MDA Library, Student Center North, Student Center South, UC Satellite, Engineering D, Engineering D2, Engineering D3, Farish Hall, and Hilton
- Replace all existing building Wi-Fi access points to Aruba 802.11ac Wave 2
- Install additional access points to cover room at capacity in academic, research, and administrative areas
Major Milestones
ACTIVITY | START | END | NOTES |
---|---|---|---|
MD Anderson Library 509 | 7/5/16 | 7/22/16 | Complete |
UC South 565 | 7/13/16 | 7/19/16 | Complete |
UC North 487 | 7/19/16 | 7/20/16 | Complete |
UC Satillite 567 | 7/20/16 | 7/22/16 | Complete |
ENG 1 579 | 7/5/16 | 7/22/16 | Complete |
ENG 2 580 | 7/19/16 | 7/19/16 | Complete |
ENG 3 581 | 7/20/16 | 7/27/16 | Complete |
Hilton 590 | 7/20/16 | 8/4/16 | Complete |
Farish 587 | 7/14/16 | 7/25/16 | Complete |
All Buildings | 7/26/16 | 8/11/16 | Complete |
Project End | 8/10/16 | Project is complete |