SR1 Life Safety Project Updates:
- The basement mechanical room air handler has been monitored daily while awaiting parts to fix current issues - Complete
- The 5th floor mechanical room air handler has been monitored daily while awaiting parts to fix current issues - Complete
- HVAC repairs and replacement are ongoing throughout the building and are being scheduled through NSM for access to certain areas
- Basement mechanical room work is ongoing – Electrical is still being completed
- Testing and Inspections of the Entire Life Safety System by the UH Fire Marshal – Is ongoing and will be completed by the end of the year
- The general refresh being done to the building restrooms is currently in the construction phase
- The stairwell refresh is ongoing – Facilities Management is working with contractors
- Loading dock door will be retrofitted with new continuous locking hardware pending funding – zone managers will be securing doors nightly until retrofit is complete -- Complete
- Exterior paving project is currently undergoing project scope development
- Seventh Floor Life Safety and Mechanical Work is ongoing
- 3rd Floor South Life Safety work is ongoing -- Mechanical for this area has not yet started
- 11/15 & 11/16 Electrical Shutdown occurred. There were problems with the generator during this shutdown which will require some of the work that was going to be completed to be completed in a future electrical shutdown
Please report any facility issues to your Building Coordinators (Fred McGhee, 713-743-8631, or Mike Mahanay, 713-743-3718) and the UH Facilities Service Center at 713-743-4948
Thank you in advance to our building occupants and stakeholders for your continued patience during this on-going process. For more information, see SR1 Life Safety Updates project.