As soon as the spring semester ended in May, Facilities Services had a huge project
of turning around 3,500 living spaces properly within only 19 days. This process ensures
a quality living space for the next wave of residents by implementing necessary repairs,
changes, and accommodations. Theses spaces were located within Cougar Place, Cougar
Village 1, Cougar Village 2 and the North Tower of Moody.
The previous process of make-ready completion involved only one skill-trades group
completing all crafts. The original plan of make readies would not be efficient to
meet the deadline at hand. The new process lead with the idea of teamwork that incorporated
a collaboration of multiple shops working together. The major adjustment was the division
of work by crafts which will have the electricians and plumbers walking each unit
and completing their respective parts such as lighting, power issues, water leaks,
and clogged drains. This leaves the one group of skill-trades completing general maintenance
issues and painting, while custodial and final inspections were the last of the crews
to complete the new process.
Implementation of this process worked three times as fast because general maintenance
was no longer doing everything throughout the space. What previously took general
maintenance one hour now only took 20 minutes because of the added support. The crews
never overlapped each other while working allowing space for each team to complete
their job. What also helped was that all parts, supplies, and paint were ordered ahead
of time based on the items purchased in the previous year. These orders were placed
by reviewing the amount of items purchased in the previous year. This eliminated a
much longer wait time.
There were several meetings every week planning for this new make ready process. It
was an amazing team effort and many General Maintenance crew members stepped up to
help fill supervisor type responsibilities during this project. General Maintenance
Supervisor Jack Enochs’ take on this process is that, “If we can all do this as a
team, we can do things that might look impossible”. With such great progress from
this process it is expected that this new process will be used in the future.