Overall Project Status: In Progress

Project Goals & Objectives

  • Meet or exceed our SLA of minimum 5Mbps in all academic and research areas
  • Upgrade Wi-Fi access points and cover rooms at capacity in all academic and research areas

Scope of Work

  • Buildings: Science and Research 1, Science and Research 2, Fleming, Health and Biomedical Sciences, Science and Teaching Lab, SERC, SEC, PGH, and Garrison (CASA)
  • Upgrade of 170 existing access points to 802.11n, move them below the ceiling to meet current design standards, and install 165 additional access points

Major Milestones

ACTIVITYSTARTENDNOTES
SR1 550 6/1/16 6/29/16 SR1 will be substantially completed on Wednesday 6/29
Fleming 564 6/1/16 6/30/16 Fleming will be substantially completed on Thursday 6/30
SR2 551 6/4/16 6/30/16 SR2 will be substantially completed on Thursday 6/30
Garrison 532 6/4/16 6/29/16 Garrison will be substantially completed on Wednesday 6/29
HSC 593 6/5/16 6/29/16 HSC will be substantially completed on Wednesday 6/29
PGH 547 6/6/16 7/1/16 PGH will be substantially completed on Friday 6/31
SEC 545 6/20/16 7/1/16 SEC will be substantially completed on Friday 7/01.
SERC 545 6/7/16 7/12/16 SERC will be substantially completed on Friday 7/12
STL 6/8/16 7/12/16 STL will be substantially completed on Wednesday 7/12 i
All Buildings 7/13/16 8/9/16 QA and configurations in all buildings
Project End 8/10/16 Project will be substantially completed on Wednesday 8/10