CAMPUS LANDSCAPE IMPROVEMENTS CONTINUE
Construction continues on the campus
beautification and landscaping
project. Funded by Ike damage
insurance funds, improvements
include the removal of trees and
plantings damaged by Hurricane Ike,
new landscape plantings and
repair/replacement of irrigation
systems to support those plantings.
Special considerations are being
given to the central E. Cullen plaza
area and the east perimeter along
Spur 5 and University Drive. Damaged
trees were removed in July and
August. Irrigation repair and new
plantings are well underway.
There has been a tremendous amount
of progress over the past several
months as crews have finished
working in Cullen Plaza and Entrance
14. Planting along Spur 5 and
Wheeler are completed, and the final
repairs to the irrigation system are
being performed.
As the final month of the project
approaches, crews will be
concentrating on the University
Drive esplanades. Between Calhoun
and Spur 5, the majority of the work
will be on retrofitting the existing
irrigation system and straightening
leaning trees. The esplanade in
front of the Campus Recreation and
Wellness Center will be re-graded,
have sod installed, and the
landscape beds will be re-planted
with Lily-of-the-Nile.
Starting at Calhoun Road and
extending to the E. Cullen Building,
new irrigation will be installed to
replace the largely non-functioning
system. This is part of a larger
campus-wide project that will allow
the university to better control its
water use through a centralized
system. The crews will also put the
final touches on the landscaping
around the new granite signage.
This project is being installed by
Landscape Art, a Houston-area
commercial landscape contractor. The
large trees from Scott Street were
relocated by Environmental Design.
Drawings were prepared by Clark
Condon Associates, Landscape
Architects. The project is being
managed by UH staffers Roger Warner
and Neal Smith. Matt Theron, UH
skilled trades, has been an
invaluable help with his campus
irrigation expertise.
This project is scheduled to be
completed by mid-January 2011. We
are moving right along toward
becoming a Tier One University!
|