| Spring 2011 |
Receive approval from SGA for second phase of UC Fee to bring UC Fee to $135 per fall and spring semester and $67.50 per summer semester. |
| |
Advertise for and select Professional Architecture and Design Team |
| |
Advertise for and select Construction Team |
| |
|
| Summer 2011 |
Program Confirmation and Concept Design for both phases |
| |
Comprehensive Document Design for both phases |
| |
Consideration and Approval from Board of Regents |
| |
|
| Winter 2012 |
Consideration and Approval from Texas Higher Education Coordinating Board |
| |
|
| Summer 2012 |
Construction begins on Phase 1 (18 months) |
| |
|
| Jan. 2014 |
Grand opening of Phase 1 |
| |
Construction begins on Phase 2 (12 months) |
| |
|
| Jan. 2015 |
Grand opening of Phase 2 |
| |
Substantial Completion of UC Transformation Project |