This page contains a list of scheduled project events, and key milestones and deliverables.

In addition, we maintain the following prioritized lists of what we're working on this week, and what we plan to do next week:

This week

  1. set up payload 1
  2. work on Discussion page of Project Web
  3. work on tracking page of Project Web
  4. wait for launch conditions

Next week

  1. check out payload 2
  2. check out payload 3
  3. work on dmaisr
  4. refurbish payload 1
  5. review flight 1 data
Back to Top

Events

Monday 2/1/99, 11:00 am

Deliver Reeldown #1 to NSBF for testing
Location: NSBF

Monday 3/29/99, 11:00 am

Deliver Payload #1 to NSBF for Preliminary Integration, T & E.
Location: NSBF

Monday 5/17/99, 11:00 am

Deliver Payload #1 to NSBF for Final Integration, T & E.
Location: NSBF

Monday 7/05/99, 11:00 am

Deliver Payloads #2 & 3 to NSBF for Final Integration, T & E.
Location: NSBF

Sunday 6/06/99 - Monday 6/21/99

First Launch Window, Priority 2 (note dates on flight request are in UT!)
Location: Palestine, Texas

Monday 7/05/99 - Wednesday 7/21/99

Second Launch Window, Priority 4 (note dates on flight request are in UT!)
Location: Will not be used

Wednesday 7/28/99

UH Team Arrive Ottumwa, Iowa

Tuesday 8/03/99 - Thursday 8/19/99

Third Launch Window, Priority 1 (note dates on flight request are in UT!)
Location: Ottumwa, Iowa

Thursday 9/02/99 - Friday 9/17/99

Fourth Launch Window, Priority 3 (note dates on flight request are in UT!)
Location: TBD

Back to Top

Milestones and Deliverables

Q1 -- Reeldown #1

Completed.

Q2 -- Payload 1

Mark 1 Completed. Now being revised to reflect upgrades and design inprovements.
Projected completion: June 2, 1999.

Q3 -- Data Encoding program

Problems with dmaisr
Projected completetion date: July 28, 1999.

Q4 -- PCM Decoder Hardware

Completed
Testing and Evaluation in Progress

Q5 -- PCM Decoder Software v 1.0

Debugging in Progress

Q5 -- Mark 2 upgrades, Payloads 2 & 3

Delayed.
Projected completion date: June 21, 1999.