Stadium Construction Work to Temporarily Affect Some Spaces in Lot 12A


Stadium construction will affect parking lot 12A beginning Saturday, Dec. 21. This work will be completed in three phases and is expected to be completed by Friday, Jan. 10.

Phase 1, which is marked in red on the plan below, will take place Dec. 21-27 and will impact 74 parking spaces.

Phase 2, which is marked in blue, will take place Dec. 27-Jan. 3 and will impact eight parking spaces. This work will require a posted flagman at the Scott Street entry to direct vehicles entering and exiting the parking lot.

Phase 3, which is marked in green, will take place Jan. 3-10 and will impact no parking spaces. This work will require closing the Cougar Place entry into the parking lot; however the Scott Street entry will remain open through all phases.

Contact Project Manager Lane Welter with any questions related to this project at lewelter@central.uh.edu or 713-743-5938. For more construction project information, visit the Facilities Planning and Construction website or visit the Plant Operations Facebook page.