UPS equipment re-energized. UH Facilities_Electrical Department was conducting a planned maintenance.

Affected Services

  • UH Wired network
  • UHSecure Wireless network
  • UH Wireless network

Event Updates

UnavailablePower Disruption/RLH network availability Outage
February 6, 2014 , 5:00 AM
Network management tools indicated an event affecting network access at Moody Towers, Bates Hall, and Settegast Hall. Additionally 5 access switches in Phillip Guthrie Hoffman Hall are offline. The Informatiion Technology Availability Center queried Facilities Customer Services for information and was informed that a scheduled/planned electrical outage took place in the RLH area of campus. UiT technical support was contacted and is in route to campus for investigation.
UnavailablePower Disruption/RLH network availability Outage
February 6, 2014 , 8:00 AM
Network operations technical support have re-energized network equipment in Settegast and Bates Hall. Network access at both buildings has been re-established. Moody Towers and PGH are under investigation.
ResolvedPower Disruption/RLH network availability Outage
February 6, 2014 , 8:30 AM
UiT technicians restored service to all affected buildings.