E. Cullen ADA Ramp and Retaining Wall Update

09-11-2017

  • Funding from MPEC received in September 2017
  • Executed agreement with contractor expected by the end of October 2017
  • Notice to Proceed revised to November 2017
  • Construction start revised to begin November 2017
  • Construction revised to end January 2018

06-20-2017

  • Procurement of Contractor pending approval from MPEC committee meeting on June 23, 2017
  • Funding approval from MPEC committee required on June 23, 2017
  • Notice to Proceed revised to August 2017
  • Construction start revised to begin August 2017
  • Construction revised to end November 2017

4-12-2017

  • Contractor Bids due April 18, 2017 
  • Expected Notice to Proceed June 2017 
  • Construction begins June 2017 
  • Construction ends August 2017

12-19-2016

  • The A/E provided drawings for the bidding that will be sent out via a Request for Proposal (RFP). 
  • The tentative construction start date is May 15, 2017 with a substantial completion date of July 31, 2017.

7-15-2016

  • Excavation of the north and south retaining walls has been completed to identify the type of wall foundation
  • Aviles Engineering will have their geotechnical report ready by Wednesday, 20 July 2016

7-6-2016

  • Excavation will start on Monday, 11 July 2016 and continue through Friday, 15 July 2016, outage submitted

6-27-2016

  • Drilling for soil samples was completed successfully on Wednesday, 22 June 2016 
  • Lab testing will take a few weeks
  • Design team met on Tuesday, 21 June 2016 and will now begin the development of the design backgrounds and drawings

6-17-2016

  • Kick-off Meeting for project scheduled for 20 June 2016
  • Drilling date for soil samples scheduled for 22 June 2016 with loading zone area and sidewalk closure needed
  • Ramp to remain closed to the exterior but will continue to serve as emergency exit for building occupants until further notice

6-1-2016