E. Cullen ADA Ramp and Retaining Wall Update
09-11-2017
- Funding from MPEC received in September 2017
- Executed agreement with contractor expected by the end of October 2017
- Notice to Proceed revised to November 2017
- Construction start revised to begin November 2017
- Construction revised to end January 2018
06-20-2017
- Procurement of Contractor pending approval from MPEC committee meeting on June 23, 2017
- Funding approval from MPEC committee required on June 23, 2017
- Notice to Proceed revised to August 2017
- Construction start revised to begin August 2017
- Construction revised to end November 2017
4-12-2017
- Contractor Bids due April 18, 2017
- Expected Notice to Proceed June 2017
- Construction begins June 2017
- Construction ends August 2017
12-19-2016
- The A/E provided drawings for the bidding that will be sent out via a Request for Proposal (RFP).
- The tentative construction start date is May 15, 2017 with a substantial completion date of July 31, 2017.
7-15-2016
- Excavation of the north and south retaining walls has been completed to identify the type of wall foundation
- Aviles Engineering will have their geotechnical report ready by Wednesday, 20 July 2016
7-6-2016
- Excavation will start on Monday, 11 July 2016 and continue through Friday, 15 July 2016, outage submitted
6-27-2016
- Drilling for soil samples was completed successfully on Wednesday, 22 June 2016
- Lab testing will take a few weeks
- Design team met on Tuesday, 21 June 2016 and will now begin the development of the design backgrounds and drawings
6-17-2016
- Kick-off Meeting for project scheduled for 20 June 2016
- Drilling date for soil samples scheduled for 22 June 2016 with loading zone area and sidewalk closure needed
- Ramp to remain closed to the exterior but will continue to serve as emergency exit for building occupants until further notice
6-1-2016
- Original outage submitted